2026-11-06
◂ Monitor BCN ASX

Beacon Minerals Limited

Ramping Producer · Gold · AU Rating locked: sign in to view v8.1 · bcn-20261104t223132-full
Last 2026-11-06
A$2.73
1D
—
1M
—
YTD
—
1Y
—
Upside
Locked: sign in to view
Mkt cap
A$317.7M
EV
A$297.9M
Cash
A$27.7M
Debt
A$7.9M

Price, volume & events

CloseVolumeFair-value rangeOverlay
Timeframe
Price style
Loading market history…
Drag to zoom · double-click to reset

Announcements

Latest 12 of 0All sources ▸
  1. No announcements are linked to this research.

Event calendar · next 12 months

7 events
TimingEventCategoryConfidenceMaterialityInvestor relevance
Q2 FY27, company guidedMaiden Lizard resource (scheduled for the December 2026 quarter)Resource Or ReserveCompany GuidedMediumAdds a new non-Iguana resource feeding the Jaurdi mill.
November 2026, company guidedJaurdi tank farm expansion (A$11.5m) commissioning, targeted for November 2026Construction Or CommissioningCompany GuidedHighPlant capacity needed for the 1.2 Mtpa Iguana ore rate; a slip delays Iguana ramp-up.
First half of FY27, company guidedIguana mineral resource update (expected in the first half of FY27)Resource Or ReserveCompany GuidedHighPost-drilling resource update of the 533 koz Iguana resource that underpins the reserve and mine life.
Quarter ends 31 Dec 2026; report late January 2027December 2026 quarter production and cost report (guidance 5,500-6,500 oz)ProductionCompany GuidedHighFirst full quarter after the tank farm commissioning; tests the 5,500-6,500 oz guidance and cost base.
ASX Listing Rule deadline 28 Feb 2027Half-year report for the six months to 31 Dec 2026 (ASX deadline 28 Feb 2027)ResultsConfirmedHighFirst half FY27 results, cash, costs and the Iguana ramp-up.
March 2027, company guidedGeko paleochannel water pipeline commissioning (planned March 2027)Construction Or CommissioningCompany GuidedMediumSecures better-quality process water at 60 l/s and rests the Jaurdi paleochannel aquifer.
Q4 FY27, company guidedMt Dimer prospect drilling (Q4 FY27, after heritage surveys)ExplorationCompany GuidedMediumTests the non-reserve Mt Dimer resource that underpins the resource calibration.

Executive roster

As of 2026-11-04Background checks ▸

Directors and key management personnel per note 25 of the FY26 annual report, plus the company secretary; the general manager (Darren Gaby) retired on 31 Aug 2026 and is excluded; non-executive directors other than the company secretary are not listed.

ExecutiveTitleNormalized roleAppointedSources
Graham McGarryExecutive Chairman / Managing DirectorExecutive Director · Chief Executive2012-03-19Beacon Minerals Annual Report 2026 (year to 30 June 2026)
Sarah ShipwayCompany Secretary (also non-executive director)Company Secretary2012-03-19Beacon Minerals Annual Report 2026 (year to 30 June 2026)