2026-11-06
◂ Monitor BTR ASX

Brightstar Resources Limited

Construction · Gold · AU Rating locked: sign in to view v8.1 · btr-20261104t223121-full
Last 2026-11-06
A$0.615
1D
—
1M
—
YTD
—
1Y
—
Upside
Locked: sign in to view
Mkt cap
A$782.3M
EV
A$895.7M
Cash
A$58.7M
Debt
A$160.1M
2 newer ASX announcements not yet reflected in this valuation

Price, volume & events

CloseVolumeFair-value rangeOverlay
Timeframe
Price style
Loading market history…
Drag to zoom · double-click to reset

Event calendar · next 12 months

6 events
TimingEventCategoryConfidenceMaterialityInvestor relevance
Late CY26Lord Byron open pit mining starts (late CY26)ProductionCompany GuidedMediumStarts ore stockpiling ahead of mill commissioning in June 2027.
December 2026 quarterSandstone Mineral Resource update (growth-focused, December 2026 quarter)Resource Or ReserveCompany GuidedHighNext Sandstone resource update after the Two Mile Hill deep drilling and the 1.45Moz Two Mile Hill-Shillington resource; drives the PFS inputs.
December 2026 quarterSandstone PFS and maiden Ore Reserve (December 2026 quarter)StudyCompany GuidedHighFirst economic study and maiden Ore Reserve for Sandstone; sets the basis for the late-CY27 FID and the Sandstone funding case.
22 Dec 2026Option expiry: 8.63m options at A$0.24 expire 22 December 2026FinancingConfirmedMediumExpiry of 8.6m A$0.24 options; in the money at A$0.555, so exercise adds about A$2.1m and shares.
Early CY27Fish underground stoping restarts (early CY27)ProductionCompany GuidedMediumRestarts high-grade feed for the Laverton plant at commissioning.
Mid CY27 to June quarter 2027Laverton 1.5Mtpa plant commissioning and first gold (June quarter CY27)Construction Or CommissioningCompany GuidedHighFirst gold and the start of the DFS 2.0 cash flows; cost and schedule risk is concentrated in the commissioning window.

Executive roster

As of 2026-11-04Background checks ▸

Executives named in the FY2026 annual report and the local management assessment (current team; Dean Vallve departed September 2025 and is excluded). Not exhaustive: senior managers below the named team are not disclosed in the documents read.

ExecutiveTitleNormalized roleAppointedSources
Alex RoviraManaging DirectorExecutive Director · Chief Executive—Annual Report to shareholders_15128bf1ddb0c7bd · Local management assessment and background checks for the current executive team
Andrew RichExecutive Director - OperationsExecutive Director · Operations—Annual Report to shareholders_15128bf1ddb0c7bd · Local management assessment and background checks for the current executive team
Nicky MartinChief Financial OfficerFinance—Local management assessment and background checks for the current executive team
Benjamin SmithCompany SecretaryCompany Secretary—Annual Report to shareholders_15128bf1ddb0c7bd · Local management assessment and background checks for the current executive team
Daniel JolleyProject DirectorOperations · Senior Management2025-11-03Local management assessment and background checks for the current executive team
John CroallGeneral Manager MiningOperations · Senior Management2025-11-03Local management assessment and background checks for the current executive team
Jonathan GoughGeneral Manager GeologyTechnical · Senior Management—Local management assessment and background checks for the current executive team
Katherine HughesChief Human Resources OfficerSenior Management—Local management assessment and background checks for the current executive team
Brendan BowEnvironment & Approvals ManagerSenior Management—Local management assessment and background checks for the current executive team
Samuel MainCorporate Development OfficerCommercial—Local management assessment and background checks for the current executive team

devCoverage status: Partial