OREMAVEN
XMM 7,722.00 -2.63% YTD +5.6% OM ASX 450.55 -2.56% YTD +0.1% OM PRECIOUS 349.20 -2.24% YTD +2.5% OM EX-PREC 418.91 -2.72% YTD -1.1% XAU 4,115.59 +2.31% YTD -4.9% GLD 375.49 +0.81% YTD -5.2% GDX 85.75 +1.37% YTD -0.0% SIL 77.33 -1.00% YTD -7.3% COPX 70.23 -5.81% YTD -1.8% URNM 40.07 -2.79% YTD -27.0%
2026-11-06
◂ Monitor LOT ASX

Lotus Resources Limited

Ramping Producer · Uranium · MW · BW Rating locked: sign in to view v8.1 · lot-20261031t153936-full
Last 2026-11-06
A$0.18
1D
—
1M
—
YTD
—
1Y
—
Upside
Locked: sign in to view
Mkt cap
A$98.5M
EV
A$86.9M
Cash
A$57.4M
Debt
A$45.8M
1 newer ASX announcement not yet reflected in this valuation

Portfolio detail

Assets

2 assets

Core asset

Kayelekera Uranium Mine

MW

Ramping Producer85% ownedUranium

Restarted September 2025; production paused June 2026 for acid supply and plant issues; resumed August 2026 at reduced rate. First export shipment (about 145klb, Orano CE) scheduled for the mid-December 2026 quarter; steady-state target 2.4Mlb a year late CY2026 onward.

Producer · Ramping producer
Production annualised (attributable)
346.1k lbd
Production (last FY, 100%)
332.1k lb
AISC (latest quarter)
—
AISC margin at spot
—
Delivery vs guidance
—
Reserve life
67.8 yrsd
Head grade
803 ppm
Resources & reserves4
TypeCategoryQuantityGradeContained mineralsDate
Mineral Resourcetotal (incl. reserves), 100% basis41.6 Mt490 ppm U3O8Uranium2026-06-30
Mineral Resourcemeasured and indicated (incl. RoM)30.9 Mt528 ppm U3O8 (derived)Uranium2026-06-30
Mineral Resourceinferred (incl. low-grade stockpiles)10.7 Mt377 ppm U3O8 (derived)Uranium2026-06-30
Ore Reserveproved and probable incl. RoM stockpile, 100% basis15.4 Mt663 ppm U3O8Uranium2026-06-30
Milestones2
  1. First uranium export shipment (about 145klb) from Walvis Bay

    Pending · High materiality

  2. Steady-state production of about 200klb a month

    Pending · High materiality

Permits & approvals1
PermitJurisdictionStatusExpiryCritical path
Malawi atomic energy regulator approval and Zambia, Namibia transport and export approvals for uranium shipmentMalawi / Zambia / NamibiaGranted—No

Core asset

Letlhakane Uranium Project

BW

Scoping Study Developer100% ownedUranium

Scoping study (March 2025) defines a 10-year, about 2.9Mlb a year case. Resource conversion drilling was not complete at 30 June 2026 and no Ore Reserve is declared.

Resource / scoping · Scoping study developer
Contained metal (attributable)
113.7m lbd
Resource grade
363 ppm
% Measured + Indicated
50%d
Resource tonnes
142.20 Mt
Our value per attrib. contained unit
Locked
Mining method
open pit: truck-and-shovel waste, continuous surface miners for ore, heap leach processings
Published study economicsIssuer or study metrics
Initial capexUS$465.4MPublished capital estimate
Operating cost41.1USD/lb

Scoping study selected case about US$65/lb; total cash cost, not AISC; NPV, IRR and discount rate not disclosed in the study pages read.

Resources & reserves3
TypeCategoryQuantityGradeContained mineralsDate
Mineral Resourceindicated71.6 Mt360 ppm U3O8Uranium2026-06-30
Mineral Resourceinferred70.6 Mt366 ppm U3O8Uranium2026-06-30
Mineral Resourcetotal142.2 Mt363 ppm U3O8Uranium2026-06-30
Economic studies1
StudyStageStatusDateSummary
Updated Letlhakane Scoping StudyScoping StudyCurrent2025-03-12Selected case about US$65/lb: 10-year life, 2.9Mlb a year average, 28.9Mlb life-of-mine, US$465.4M initial capital, total cash cost US$41.1/lb. AACE Class 5 (+/-30%). NPV and IRR not disclosed in the pages read.