Vulcan Energy Resources Limited

Construction · Lithium · DE · FR · IT Rating locked: sign in to view v8.1 · vul-20261031t172753-full
Last 2026-11-06
A$1.115
1D
—
1M
—
YTD
—
1Y
—
Upside
Locked: sign in to view
Mkt cap
A$533.7M
EV
A$239.3M
Cash
€129.4M
Debt
€0

Price, volume & events

CloseVolumeFair-value rangeOverlay
Timeframe
Price style
Loading market history…
Drag to zoom · double-click to reset

Announcements

Latest 12 of 13All sources ▸
  1. Quarterly Activities Report - Period Ending 30 September 2026Operations
  2. Quarterly Cashflow Report - Period Ending 30 September 2026Results
  3. Corporate Presentation - Q4 2026Presentation
  4. Half Year Report for the Period Ending 30 June 2026Results
  5. Interim Management Report 2026Governance
  6. Phase Two Preliminary Feasibility Study (Project Ludwig)Study
  7. Quarterly Cashflow Report - Period Ending 30 June 2026Results
  8. Quarterly Cashflow Report - Period Ending 31 March 2026Results
  9. German State grants royalty exemption for lithium productionPermitting
  10. Annual Report - Period Ending 31 December 2025Results
  11. Quarterly Cashflow Report Period Ending 31 December 2025Results
  12. Opening of Retail Entitlement Offer (financing and FID presentation, offer booklet)Financing

Event calendar · next 12 months

12 events
TimingEventCategoryConfidenceMaterialityInvestor relevance
Q4 2026ABB main electrical supply contract awardConstruction Or CommissioningCompany GuidedMediumLast major supply contract; cost certainty against the EUR1,476m capex budget.
before 31 December 2026EUR80m term deposits become accessible within 90 daysFinancingCompany GuidedMediumLifts accessible liquidity from EUR129.4m cash toward EUR209.4m.
Q4 2026Start of ICPP section 2 pipeline constructionConstruction Or CommissioningCompany GuidedMediumPipeline sections link the wells to the plant; on-time starts support the 2028 first-production date.
Q4 2026Award of ICPP sections 3 to 7 contractsConstruction Or CommissioningCompany GuidedMediumFixes the price of the remaining pipeline scope against the EUR257m ICPP budget.
end of Q4 2026Insheim power plant returns to service after maintenanceProductionCompany GuidedMediumRestores the existing renewable-power revenue and proves reliability of the field.
Q4 2026Second drill rig V10 mobilises to the Trappelberg well siteConstruction Or CommissioningCompany GuidedMediumDoubles drilling capacity for the production and re-injection wells that set field deliverability.
12.2026 expiryWaldnerturm and Loewenherz exploration licences reach expiryPermittingCompany GuidedMediumPortfolio review aims to relinquish weaker licences; renewals or lapses change the future-phase pipeline.
Q1 2027First senior debt drawdown and further strategic equity instalmentsFinancingCompany GuidedHighStarts the EUR1,185m debt draw that funds most remaining capex; milestone conditions must be met.
late January to March 2027 (customary timing)FY2026 annual report and December 2026 quarterly reportResultsInferredMediumUpdates capex-to-date, cash and construction progress against the budget profile.
Q3 2027Completion of ICPP section 1Construction Or CommissioningCompany GuidedMediumFirst physical pipeline delivery milestone on the way to mechanical completion.
no date givenLudwig asset-level strategic partner selectionFinancingCompany GuidedMediumA partner for Ludwig determines the retained interest and funding of Phase Two.
subject to appeal, no date givenAppeal outcome on the French (Nancy) geothermal and lithium permit decisionsPermittingCompany GuidedMediumThe court decision cuts against the Kachelhoffa licence; appeals are pending.

Executive roster

As of 2026-10-30Background checks ▸

Executive directors, group executives and company secretary named in the annual report, the September 2026 board succession and the October 2026 corporate presentation; non-executive directors excluded. Appointment dates are given only where disclosed.

ExecutiveTitleNormalized roleAppointedSources
Cris MorenoManaging Director and Group Chief Executive OfficerExecutive Director · Chief Executive—Corporate Presentation - Q4 2026 · Half Year Report for the Period Ending 30 June 2026
Felicity GoodingExecutive Director and Group Chief Financial OfficerExecutive Director · Finance—Corporate Presentation - Q4 2026 · Half Year Report for the Period Ending 30 June 2026
Dr Francis WedinFounder (previously Executive Chair until 10 September 2026)Senior Management—Quarterly Activities Report - Period Ending 30 September 2026 · Half Year Report for the Period Ending 30 June 2026
Daniel TyddeCompany Secretary and General CounselCompany Secretary—Annual Report - Period Ending 31 December 2025 · Half Year Report for the Period Ending 30 June 2026
Carsten BachgChief Operating OfficerOperations—Corporate Presentation - Q4 2026
Manfred BoeckmannChief Commercial OfficerCommercial—Corporate Presentation - Q4 2026
Thorsten WeimannChief Development OfficerTechnical—Corporate Presentation - Q4 2026
Dr Horst KreuterChief Representative Germany and Board advisorSenior Management—Annual Report - Period Ending 31 December 2025

devCoverage status: Complete As Disclosed